Review of Tecon Santos 10 rules moves the terminal tender to 2027

The publication of the tender notice for the Port of Santos's new container terminal was moved to early 2027 while the government reassesses the competition model and awaits a new review by the TCU.

Editorial view of a container terminal at the Port of Santos, with ships and cranes along the quay
Contêm Insights Editorial

The federal government is expected to publish in early 2027 the tender notice for the auction of Tecon Santos 10, a new container terminal planned for the Port of Santos. The information was disclosed on November 26 by the Minister of Ports and Airports, Tomé Franca, during an infrastructure-sector event.

The previous expectation was to complete and publish the rules in 2026. The delay followed a reassessment of the project's competition model, which was discussed by a working group over recent months.

The proposal originally prepared by the National Waterway Transport Agency (Antaq) provided for two stages in the auction. In the first, terminal operators and shipping lines already present in the port complex would face restrictions. These groups could participate in a second phase if there were no winning bids initially.

In May, the Civil House recommended a more open format, with participation by all interested parties conditional on the divestment of existing assets in the complex by companies already operating there. The change led to a review of the previously approved model and will require a new assessment by the Federal Court of Accounts (TCU) before the tender notice is published.

The project is planned for the Saboó area, on the right bank of the port. According to information gathered by the sources, the development should occupy about 622,000 square meters, have an estimated dynamic capacity of 3.25 million TEUs per year, and operate under a 25-year lease contract. Projected investments are approximately R$ 6.47 billion, while the estimated total contract value exceeds R$ 43.6 billion.

The expansion is being planned as container handling at Santos increases. Between January and August 2026, the complex handled 4.007 million TEUs, up 3.9% from the same period in 2025, when 3.856 million TEUs were recorded.

The port's installed capacity is estimated at 5.76 million TEUs per year and, according to an assessment cited by the sources, may meet projected demand only through 2028. Because port developments of this size take an average of five years to begin operating, the review of the rules makes the expansion schedule more time-sensitive.

While the new terminal awaits the tender notice, operators already established at the port are also expanding their facilities. DP World expects to invest more than R$ 2 billion in the expansion and modernization of its terminal in Santos, increasing capacity from 1.4 million to 2.1 million TEUs by 2028.

The tender notice still depends on the government's completion of the model, its submission to Antaq, and the new TCU review. Publication at the beginning of 2027 will therefore be the next stage of a project that has been under discussion for more than a decade.